Project Description

The 4.6 m Dia by 41m long formwork on the outlet line and 4.6 Dia by 18 m long formwork on the inlet line was designed to be fully encased in concrete in order to connect the seawater lift pump station with the subsea tunnels. The formers were manufactured by RPC Technologies for Thiess Degrémont Joint Venture as part of the Victorian Desalination Project.